Project Schedule

All first part, Section 520, roadway, bridge and intersection work has been completed. Landscaping/plantings will finish in fall 2015.

Part two, Section 510, is under design and expected to be under construction in early 2017. Scheduling for Section 510 work will be posted once it is available.



 

Section 520 (Completed)

Stages 3F, 4B and 4C Construction

Click to enlarge.

Stage 1A,B,C,D – April 2013 to December 2013 –  COMPLETED*

Elm Street to north of Harding Blvd./Spruce Street

  • First build parking lot at Harding Blvd. and Markley Street/U.S. Route 202 South
  • Then reconstruct
    • West, Middle, East sides
  • Work area includes intersection of Markley/Harding/Spruce
  • Reconstruct/realign intersection of Coolidge Blvd. and Markley Street

Click to enlarge.

Construction Completed on the Main Street Bridge over Stony Creek

Stage M1 – April 2013 to July 2013

  • Rehab North side of bridge
  • Maintain one lane in each direction on bridge

Stage M2 – July 2013 to August 2014

  • Rehab South side of bridge
  • Maintain one lane in each direction on bridge

A typical intersection improvement


All Section 520 Construction Stages


Click to enlarge.

Stage 2 – January 2014 to March 2014 – COMPLETED*


Click to enlarge.

North of Harding Blvd./Spruce Street to Lincoln Avenue

  • Reconstruct East side
  • Install bump out parking

Detour is in place July ‘13 to July ’16


Stage 3


Stages 3&4 Click to enlarge.

Stage 3A – March 2014 to April 2014 – COMPLETED*
North of Harding/Spruce to north of Sterigere Street

  • Reconstruct West side
  • Install bump out parking

Stage 3B – April 2014 to July 2014 – COMPLETED*
North of Sterigere Street to north of Fornance Street

  • Reconstruct West side
  • Install bump out parking

Stage 3C – April 2014 to November 2014 – COMPLETED*
North of Fornance Street to Roberts Street

  • Reconstruct West side
  • Install bump out parking

Stage 3D – September 2014 to December 2014 – COMPLETED*
Roberts to South of Johnson Hwy.

  • Reconstruct West side
  • Reconstruct and widen South side of W. Johnson Hwy.

Stage 3E – December 2014 – COMPLETED*
Roberts to South of Johnson Hwy.

  • Reconstruct Middle of Markley Street

Stage 3F – April 2015 to June 2015 – COMPLETED
Reconstruct North side of W. Johnson Hwy.

  • Widen west side of Swede Road

 

Stage 4A – July 2014 to September 2014  – COMPLETED*
Lincoln Avenue to Wood Street

  • Reconstruct east side
  • Install bump out parking

Stage 4B – July 2014 to Spring 2015 – COMPLETED
Wood Street to Fornance Street

  • Reconstruct East side
  • Install bump out parking

Stage 4C – October 2015 to April 2016 – COMPLETED IN 2015
Fornance Street to Roberts Street

  • Reconstruct East side and Middle
  • Install bump out parking

Stage 4D – April 2016 to June 2016 – COMPLETED IN 2015
Roberts Street to Johnson Hwy.

  • Reconstruct East side
  • Widen east side of Markley Street/U.S. 202 South at Johnson Hwy.
  • Widen south side of Johnson Hwy. at Markley Street

Stage 4E – June 2016 to July 2016 – COMPLETED IN 2015
Johnson Hwy. and Swede Road

  • Widen North side of Johnson Hwy. at intersection
  • Widen east side of Swede Road at intersection

 

Stage 5 – July 2016 to September 2016 – COMPLETED IN 2015


Click to enlarge.

Markley Street, Johnson Highway and Swede Road

  • Final paving and line striping on Markley Street
  • Mill and overlay Swede Road north of Johnson Hwy.
  • Line striping on Johnson Hwy.

 


 

Main Street Bridge over Stony Creek

Stage M1 – May 2013 to October 2013 – COMPLETED

  • Rehab North side of bridge
  • Maintain one lane in each direction on bridge

Stage M2 – October 2013 – COMPLETED

  • Rehab Middle section of bridge
  • Maintain one lane in each direction on bridge

Stage M3 – October 2013 to April 2014 – COMPLETED

  • Rehab South side of bridge
  • Maintain one lane in each direction on bridge

Stage M4 – April 2014 – COMPLETED

  • Pave west approach
  • Maintain one lane in each direction on bridge

* Final riding surface paving on Markley Street will be placed on the entire project at the completion of all stages.